Unit 6 Assignment: Operational Issues in Supply Chain Management

MT433-3: Evaluate operational issues in supply chain management.

Being able to calculate production levels and inventory costs is a key component of evaluating the fit of various options to business scenarios. For this assignment, answer the two problems below. Use the template provided to fill in both your answers and your work. If you do not use the template or do not show your work, you will lose points.

Don't use plagiarized sources. Get Your Custom Essay on
Unit 6 Assignment: Operational Issues in Supply Chain Management
Get an essay WRITTEN FOR YOU, Plagiarism free, and by an EXPERT!
Order Essay

Problem 1

Based on the demand shown below, use a (a) chase production strategy and (b) level production strategy to compute the monthly production, ending inventory or backlog, and workforce levels. A worker can produce 50 units per month. Beginning inventory in January is 500 units, and the firm is targeting 200 units of inventory at the end of June.

***Table in additional material***

Problem 2

Given the following information, compute the economic order quantity, annual holding cost, annual order cost, and annual total inventory cost.

Annual requirements (R) = 50,000 units

Order cost (S) = $150 per order

Holding rate (k) = 15%

Unit cost (c) = $100 per unit

*Please use grading rubric for unit 6 that is located in the additional materials*

ANSWER

 

 

 

 

 

 

 

MT433 – Global Supply Chain Management

 

Unit 6 Assignment

 

Student Name Here

 

Purdue University Global

 

Date Submitted Here

 

 

 

 

 

 

 

Data Presentation:

Chase Strategy:

Month JAN FEB MAR APR MAY JUN
Demand

 

2000 3000 5000 6000 5000 2000
Production

 

1500 3000 5000 6000 5000 2200
Ending Inventory 0 0 0 0 0 200
Workforce

 

30 60 100 120 100 44

 

The final inventory will be calculated as; Ending inventory= Beginning inventory + Production – Demand. The workforce will be calculated by dividing the production by monthly capacity.

Level of production= 23,000

Beginning inventory= 500

Ending inventory = 200

Total months 6

(23,000-500+200)/6= 3,783

 

Month JAN FEB MAR APR MAY JUN
Demand

 

2000 3000 5000 6000 5000 2000
Production

 

3,783 3,783 3,783 3,783 3,783 3,783
Ending

Inventory

2,283 1,283 -717 -1,717 -717 2,283
Workforce

 

75 75 75 75 75 75

 

EOQ:

 

Variable Answer
EOQ 1000 Units
Annual Holding Cost $7,500
Annual Order Cost $7,500
Total Annual Inventory Cost 15,000

 

Math Work:

Chase: Workforce=production/Worker capacity

Jan – 1500/50=30

Feb – 3000/50=60

March- 5000/50=100

April- 6000/50=120

May- 5000/50=100

June- 2200/50=44

Level: (23,000-500+200)/6= 3,783

3783/50= 75

EOQ:

EOQ = √ 2 RS kC = √ 2 x50,000 x $ 150 .15 x $ 100 = √ 15,000,000 15 = √1,000,000 = 1,000 units Annual holding cost = (Q/2) x k x C = (1,000/2) x .15 x $100 = $7,500 s

Total inventory cost = 50,000 1,000 X 150+ 1,000 2 X 15 = 7,5000 + $7,500 = 15,000

 

 

Narrative

Supply chain management entails planning how the whole supply chain will function to keep customers happy and ensure that products remain cost efficient (Ivanov, Tsipoulanidis and Schönberger, 2019). To improve the supply chain efficiency, production planning is required. To balance the demands of the customers and profitability growth of a company there is need to improve the supply chain management. Demand chase strategy and level strategy are used in planning production to reduce the inventory cost. Chase strategy is used to match demand and production with the primary aim of reducing the inventory costs (Nugraha, Hisjam and Sutopo, 2020). This means matching capacity and demand period by period. Therefore, the goal of the company is to maintain a zero inventory balance each month except September when they desire 3000 units. For this strategy, the calculation process will include calculating the workforce and dividing by production by the monthly capacity. This means Workforce=production/Worker capacity.

Level production strategy relies on constant capacity and output rates while adjusting backlog and inventory levels to solve the shifting demanding signal. This strategy produces the same number of units equally and is common in industries that have cyclical demand and limited production capabilities. To maintain a zero balance inventory and a constant production rate, they need to calculate the average demand for the six months. The economic order quantity is the company’s optimal order quantity for lowering its total costs linked to receiving, ordering and inventory holding (Agarwal, 2014). Therefore, this is the quantity a company should purchase so as to minimize its inventory costs. Streamlining the supply chain allows for faster production and ability of a company to compete and create value for customers.

 

 

References

Agarwal, S. (2014). Economic order quantity model: a review. VSRD International Journal of Mechanical, Civil, Automobile and Production Engineering, 4(12), 233-236.

Ivanov, D., Tsipoulanidis, A., & Schönberger, J. (2019). Global supply chain and operations management: A decision-oriented introduction to the creation of value (Vol. 2). Cham, Switzerland: Springer International Publishing.

Nugraha, I., Hisjam, M., & Sutopo, W. (2020, October). Aggregate Planning Method as Production Quantity Planning and Control to Minimizing Cost. In IOP Conference Series: Materials Science and Engineering (Vol. 943, No. 1, p. 012045). IOP Publishing.

Homework Sharks
Order NOW For A 10% Discount!
Pages (550 words)
Approximate price: -

Our Advantages

Plagiarism Free Papers

All our papers are original and written from scratch. We will email you a plagiarism report alongside your completed paper once done.

Free Revisions

All papers are submitted ahead of time. We do this to allow you time to point out any area you would need revision on, and help you for free.

Title-page

A title page preceeds all your paper content. Here, you put all your personal information and this we give out for free.

Bibliography

Without a reference/bibliography page, any academic paper is incomplete and doesnt qualify for grading. We also offer this for free.

Originality & Security

At Homework Sharks, we take confidentiality seriously and all your personal information is stored safely and do not share it with third parties for any reasons whatsoever. Our work is original and we send plagiarism reports alongside every paper.

24/7 Customer Support

Our agents are online 24/7. Feel free to contact us through email or talk to our live agents.

Try it now!

Calculate the price of your order

We'll send you the first draft for approval by at
Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Our Services

We work around the clock to see best customer experience.

Pricing

Flexible Pricing

Our prces are pocket friendly and you can do partial payments. When that is not enough, we have a free enquiry service.

Communication

Admission help & Client-Writer Contact

When you need to elaborate something further to your writer, we provide that button.

Deadlines

Paper Submission

We take deadlines seriously and our papers are submitted ahead of time. We are happy to assist you in case of any adjustments needed.

Reviews

Customer Feedback

Your feedback, good or bad is of great concern to us and we take it very seriously. We are, therefore, constantly adjusting our policies to ensure best customer/writer experience.